North Bumby Avenue

Challenge

The City of Orlando asked for roadway reconstruction while maintaining access for residents living directly on Bumby Avenue. As always, we were up for the challenge.

Client City of Orlando
Location Orlando, FL
Contract Value $7,000,000
Schedule Apr 2015 - Apr 2017

Solution

We replaced and improved the existing drainage collection system from SR 50 (Colonial Drive) to Corrine Drive, including 1,856 linear feet of 30" RCP and 1,472 linear feet of 24" RCP; 5,000 linear feet of new water main; and complete reconstruction of 22,000 square yards of roadway. We did this through phased construction in order to provide minimal impact to the overall site.

Result

Our work resulted in improved water service and reduced flooding during heavy rain along the roadway corridor.