Small site with multiple trades working at the same time. Fire line design changes after contract award.
| Client | Turner Construction Company |
|---|---|
| Location | Orlando, FL |
| Contract Value | $1,116,922 |
|---|---|
| Schedule | Sep 2023 - Apr 2024 |
G&R worked alongside Turner to accommodate multiple trades while performing underground work onsite. G&R identified issues early on with the fire line design and worked with Turner, Orange County and the Engineer to come up with the alternate design.