Reconstruct the existing sidewalk area to a wider sidewalk while maintaining the large pedestrian volume.
| Client | Orange County Government |
|---|---|
| Location | Orlando, FL |
| Contract Value | $12,708,210 |
|---|---|
| Schedule | Nov 2022 - May 2025 |
We worked with engineers who specialize in "Maintenance of Traffic" plans to create pedestrian detour plans, block by block, to ensure safe passage of pedestrians through the project.
The pedestrians were able to navigate the project safely and without a lot of added travel distance.