Legacy Trail
Challenge
Sarasota County contracted us to design-build almost 11 miles of Legacy Trail. The project had a limited budget, a large shopping list, and limited resources.
Client | City of Sarasota |
---|---|
Location | Sarasota, FL |
Contract Value | $14,423,000 |
---|---|
Schedule | Jan 2007 - Feb 2009 |
Solution
As the single point of responsibility for the project, we constructed 10.75 miles of 12’ wide asphalt bike trail, 6 pedestrian bridges, 11 rest stations, arsenic remediation, landscaping, fencing, and new water and reclaim water mains.
Through the use of design-build delivery, contingencies, and allowances, the entire scope of work was completed for the original budgeted amount.
Result
We delivered the entire scope of work on budget and successfully added over 10 miles of bike trails to the city’s system.