Pass-a-Grille Way

Challenge

The City of St Pete Beach needed roadway construction completed through a phased approach minimizing impact to the neighbors and visitors in the area.

Client City of St. Pete Beach
Location St. Pete Beach, FL
Contract Value $10,524,776
Schedule Jan 2018 - Aug 2019

Solution

Thanks to our experience and qualifications in roadway construction, we won this bid. The project involved full-depth roadway reclamation, roadway reconstruction, stormwater, water, reclaimed water, and flood control structures. To mitigate the risk of flooding, we created and leveraged alternate drainage designs to accommodate existing utilities.

Result

The project impacted people and communities throughout Pass A Grille Way. It beautified the roadway corridor, reduced the risk of flooding, and provided improved water service to the city.