Challenge

Gibbs & Register was the selected contractor for the construction to replace the nearly 80-year-old aging infrastructure along Summerlin Avenue in downtown Orlando. The work will take place in two-block sections with temporary traffic disruptions along the project route.

Client Orlando Utilities Commission
Location Orlando, FL
Contract Value $26,528,466
Schedule Jan 2025 - In Progress

Solution

The project includes the installation of approximately 1.25 miles of new water mains, the addition of fire hydrants and the update of critical valves to improve fire safety and system dependability.

Result

This project modernizes OUC's potable water system and the City of Orlando's sanitary sewer and stormwater systems to enhance service reliability, streamline safety systems and improve quality of life for residents through infrastructure upgrades. Beyond utility upgrades, the project includes a complete restoration of the roadways, enhanced pedestrian safety and improved streetscapes.

Gracepoint Women’s Behavioral Health Hospital
Next Project
Looking for high-quality results delivered on time?
Partner with us today