Pedestrian Traffic due to the proximity to one of the largest Universities in the Country (UCF). Heavy traffic through the work zone.
| Client | Orange County Government |
|---|---|
| Location | Orlando, FL |
| Contract Value | $13,211,733 |
|---|---|
| Schedule | Oct 2023 - Mar 2025 |
G&R utilized phasing approach to alleviate traffic congestion. The footings for the railing were precasted in the yard to avoid extended sidewalk and lane closure on Alafaya Trail & University Blvd.
Expedited schedule for the trail and railing foundation work by working in phased approach and pre-work in the yard.